Hayward Industrial Estate

Client: BCH Developments

Location: Birmingham

Budget: £465,000

Duration: 24 weeks

Gillman were tasked with refurbishing the Hayward Industrial Estate to improve and modernise the estate back into lettable condition for our client

WORKS COMPLETED:

  • External decorations of the cladding, shutter doors, bollards etc
  • Installation of new shutter doors
  • Full refurbishment including new carpets, vinyl,
  • Suspended ceiling with LED lighting
  • Full Decorations including warehouse floor coating
  • Installation of new warehouse LED lighting