Hayward Industrial Estate
Client: BCH Developments
Location: Birmingham
Budget: £465,000
Duration: 24 weeks
Gillman were tasked with refurbishing the Hayward Industrial Estate to improve and modernise the estate back into lettable condition for our client
WORKS COMPLETED:
- External decorations of the cladding, shutter doors, bollards etc
- Installation of new shutter doors
- Full refurbishment including new carpets, vinyl,
- Suspended ceiling with LED lighting
- Full Decorations including warehouse floor coating
- Installation of new warehouse LED lighting